Click here to read the article.  April, 2006 - Samsung-Austin FAB2 Project Awarded.
<< Click the link to see what Texas Contractor Magazine had to say in their July 3rd issue about the Samsung-ATS team.
ATS moved onto the job site with five Soilmec drilling rigs (two 516 models and three 312 models), two Terex cranes (one 65-ton and one 60-ton), one 28-ton P&H crane, several loaders and skid steers, and a crew of 30.
ATS began drilling on May 1, and was required to have the 2,500 piers completed by June 16. "In order to keep on schedule, we must complete a minimum of 60 piers per day," said Brent Lawler, ATS Drilling Operations Manager. "That's a pretty tough schedule." Even so, they averaged 75 piers a day.
ATS had previously completed the drilling for Samsung-Austin FAB1 Project, as well as expansion of FAB1. |