August, 2008 - Austin Road and Bridge L.P. was the low bidder at $179,976,986 on an Interchange Project for IH-30 and The President George Bush Turnpike located in Dallas, Texas.  ATS Drilling L.P. was selected by Austin Road and Bridge L.P.  to do the most challenging portion of the foundation work for this project.    The scope of the foundation work awarded to ATS Drilling is constructing over 500 foundations for Main Lane Bridges which span across Lake Ray Hubbard and are more than 1 mile in total length. The project is scheduled to start in early 2009 with an estimated final completion in mid 2011.


 

July, 2008 - ATS Drilling was awarded the Port of Houston Authority – Bayport Terminal Complex – Phase 1 Wharf Project 

 


 

September, 2006 - ATS awarded one of the largest drilling contracts in Texas for the $82 million Lake Lewisville Toll Bridge, a 1.7 mile bridge over Lake Lewisville

North Texas Tollway Authority.


Click here to read the article.

April, 2006 -  Samsung-Austin FAB2 Project Awarded.

<< Click the link to see what Texas Contractor Magazine had to say in their July 3rd issue about the Samsung-ATS team.

ATS moved onto the job site with five Soilmec drilling rigs (two 516 models and three 312 models), two Terex cranes (one 65-ton and one 60-ton), one 28-ton P&H crane, several loaders and skid steers, and a crew of 30.

ATS began drilling on May 1, and was required to have the 2,500 piers completed by June 16. "In order to keep on schedule, we must complete a minimum of 60 piers per day," said Brent Lawler, ATS Drilling Operations Manager. "That's a pretty tough schedule." Even so, they averaged 75 piers a day.

ATS had previously completed the drilling for Samsung-Austin FAB1 Project, as well as expansion of FAB1.